Internal Gutting of the Chapel began on December 27th 2005
The gutting was necessary to examine masonary problems and replace all wiring.
|
The Stained Glass Windows were carefully removed and stored for refurbishment by Colorsmith Stained Glass
 |
All plaster & lath was removed by Dearborn Demolition
 |
|
The Balcony was gutted to prepare for installation of the Master Bedroom and Bath
 |
A temporary Driveway was installed by Cruz Construction
 |
|
Knob & Tube wiring was removed
 |
The pews await their new home
 photo by Bill Ackerman of Suburban Life
|